Foundation Quote Decoder · Sample teardown · Free 12-item checklist · Privacy
SAMPLE, built from two invented quotes (fictional companies) to show the format. Real teardowns use the customer's own documents.
This report compares the written quotes provided, line by line. It is a document comparison only. It is not an engineering evaluation, a home inspection, a diagnosis of any foundation condition, or a recommendation of any contractor or scope of work. Only a licensed engineer who evaluates your property can advise you on what your home needs. Figures are taken from your documents as cited; if a quote is revised, this comparison applies to the version provided.
Quotes compared: Quote A, Red River Foundation Repair (fictional), Nov 12, 2026, $13,530 · Quote B, Prairie State Foundation Co. (fictional), Nov 14, 2026, $21,530 · Difference: $8,000
The $8,000 is not one company charging more for the same job. The two documents describe different jobs. Quote B includes $4,150 of work Quote A does not quote at all (interior floor work, drainage, a plumbing test). Quote B installs 22 piers including 8 inside the house; Quote A installs 16, all outside, and prices any interior piers later as a change order. Quote B includes the engineer report and permit in its price; Quote A excludes both. Compared on the closest like-for-like basis the documents allow, the gap narrows from $8,000 to about $1,760, and several costs in Quote A are still unstated, so a true final-price comparison is not possible from these documents alone. The questions at the end are the ones that would close that gap.
| Item | Quote A | Quote B |
|---|---|---|
| Piers | 16 pressed concrete, exterior only (A1) | 22 helical, 14 exterior + 8 interior (B1) |
| Price per pier | $650 | $790 |
| Interior floor breakouts/patch | Not quoted; interior access "billed separately," rate not stated | Included, $1,900 (B2) |
| Engineer report | Excluded: homeowner provides | Included (B3) |
| City permit | Excluded | Included (B4) |
| Plumbing leak test | Not included | $550 (B5) |
| Drainage correction | Not addressed | 40 ft French drain, $1,700 (B6) |
| Root barrier | 20 ft, $980 (A3) | Not mentioned |
| Exterior access/tunneling | $1,450 (A2) | Not listed as a separate line |
| Exterior concrete repair | $700 (A4) | Interior patch in B2; exterior repair not separately listed |
| Term | Quote A | Quote B |
|---|---|---|
| Deposit at signing | 50%, $6,765 | 10%, $2,153 |
| Balance trigger | On completion | After the engineer's post-install letter is delivered |
| Warranty | Lifetime on installed piers | 25 years on installed piers |
| Warranty transfer | One transfer, $250 fee | Transfers with no fee |
| Change-order exposure | Interior piers $780 each + interior access at an unstated rate | No change-order rate stated; interior scope is inside the total |
Ask Quote A's company: (1) What is the interior access rate, in dollars? (2) What will the permit and engineer report cost me, in total? (3) If interior piers are needed, is $780/pier the complete installed price? (4) Is drainage correction needed on this house, and if so, what would it cost? Ask Quote B's company: (1) What in the engineer's findings set the count at 22 piers, and can I see that reasoning before signing? (2) If the post-install engineer recommends more piers, what do they cost each? (3) Is the French drain required for the warranty, or optional?
End of sample. Every figure above is cited to the sample quote documents (A1–A4, B1–B6 and their terms). No statement in this report says what this fictional house needs, and no statement recommends either fictional company, that is the product, on purpose.
Foundation Quote Decoder, a document-comparison service. Not an engineering, inspection, or consulting service.